HighPoint 2222 Campus
What is being built next door, and what our neighborhood is asking for.
WHY THIS MATTERS
The old 3M campus at 6801 River Place Boulevard is being turned into a high-powered computer center. It sits right next to our homes and our kids' bus routes. The company building it, SB Energy, has told investors it is a data center.
It has told our neighborhood it is a research campus. Both can be true. But families who live here deserve clear answers, written promises, and a seat at the table before the building opens. That is what we are working for.
THE SHORT VERSION
Who Owns It
SE Cosmos, LLC, a company fully owned by SB Energy. SB Energy is part of the SoftBank family of companies.
Who Will Use It
Graphcore, a computer chip company also owned by SoftBank. It will be Graphcore's U.S. engineering headquarters.
How Much Power
About 50 megawatts for computers, and about 70 megawatts in total. That is a lot of electricity for one building.
When
Construction started in 2026. The City expects the project to reach full power by 2029.
What the Permits Show
About 90 City permits so far, covering about 328,000 square feet of interior work, a 117,450 square foot outdoor equipment yard, and power equipment for at least three data halls.
What We Want
Written, enforceable promises on noise, school bus access, and other neighborhood protections.

1. WHO IS BEHIND THE PROJECT
SE Cosmos, LLC bought the property from Karlin Real Estate on March 20, 2026. SE Cosmos is not just a name on paper. It owns the land, it is the landlord, and it borrowed $999 million against the property to pay for the project. SB Energy is the developer, which means it is the company in charge of building it. SB Energy plans to spend about $1 billion on the campus, which has about 1.1 million square feet of buildings.
​
Graphcore was publicly named as the tenant on August 25, 2026. Graphcore designs computer chips and the large computer systems that use them. SB Energy's filing with the U.S. Securities and Exchange Commission (SEC) says the official renter is a SoftBank company under a 15-year lease. Public summaries of that filing name the renter as Silver Bands 3 (US) Corp., with SoftBank Group Capital Limited backing the lease. The lease was signed November 7, 2025, and has an option to add 10 more years.
​
The campus covers about 156 acres. Most of it is east of River Place Blvd. A separate piece of land on the west side is sometimes called the "Porkchop" because of its shape.

2. IS IT A DATA CENTER?
SB Energy's SEC filing lists Cosmos as one of its data centers, with about 50 megawatts of "critical IT capacity." The same filing says the building will support research, development, and engineering for advanced AI (artificial intelligence) computers.
​
The City of Austin does not yet have its own category for data centers. City staff said data centers have usually been treated as "Communications Services." In a September 24, 2026 email, Austin Planning said a data center is allowed as part of a research and development facility.
​
Here is the key point for residents: whatever it is called, this building will use a large amount of electricity and run powerful equipment around the clock, right next to homes. The public records do not say exactly how that computer power will be used. That is one of the reasons we are asking for clear, written answers.

3. HOW MUCH POWER?
There are Three Different Numbers, and it Helps to Keep Them Separate
-
About 50 megawatts for the computers themselves (the "critical IT capacity").
-
About 70 megawatts of total power the electric system is being upgraded to deliver.
-
The power the building actually uses at any moment, which nobody has made public.
​
Austin Energy, our city-owned electric company, is upgrading the substation on the campus from 20 megawatts to 70 megawatts. It will add two new transformers and upgrade an existing one. A Fitch Ratings report from May 28, 2026 said the work would happen in two steps, finishing by April 30 and October 31, 2026. Those were plans, not promises. No one has publicly confirmed that either step was finished on time.
​
Fitch also said construction would take about 12 months for the first 5 megawatts and the offices, and 13 months for the remaining 45 megawatts.
​
At our September 17, 2026 town hall at Four Points Middle School, SB Energy's Jaime Carlson said the project is 50 megawatts for computers plus 20 megawatts for the offices, for about 70 megawatts in total.

4. WHAT SB ENERGY HAS PROMISED SO FAR
SB Energy has made these public statements.
None of them are yet written into a binding agreement with the neighborhood.
-
Cooling: It will use a closed-loop, air-cooled system. (This means the cooling water is reused in sealed pipes instead of being used up.)
-
Water: It will not use more water than 3M did when 3M was here.
-
Power costs: It will pay for all the power upgrades Austin Energy needs, so regular customers do not pay for them.
-
Noise: Noise will follow Austin's rules and the original zoning for the site.
-
School buses: Leander ISD buses used to cut through the campus on a bus-only route. They stopped during construction. SB Energy says it is "still looking at potential options."
-
SB Energy has also published a "Community Compact" for the project.
These are good first steps. But statements to the press can change. Promises written into a legal agreement cannot.

5. THE RULES THAT ALREADY PROTECT US
This land has its own special rules from the 1980s
November 15, 1984 — The City passed Ordinance 841115-GG. It created a Planned Development Area for the site. It allowed offices and research labs, and it generally did not allow homes.​
​
January 1986 — The Hill Country Roadway Ordinance took effect. It protects the look and environment along roads like RM 2222.​
​
June 1986 — Ordinance 860619-Q changed the zoning to Research and Development. Council passed it June 19, 1986, and it took effect June 29, 1986.​
The 1984 agreement includes strong noise and vibration rules. Noise is measured at the property line. Limits are set for different sound pitches, and they drop by 3 decibels from 10 p.m. to 6 a.m. There are also limits on vibration. Construction noise is not covered by these limits. Council Member Marc Duchen has said these rules are in some ways stricter than Austin's regular rules, and that he expects them to be enforced.
Site History
Late 1980s — 3M built and moved into the campus.​
​
2017 — The Hill Country Roadway Ordinance took effect. It protects the look and environment along roads like RM 2222.​
​
2019 — 3M had left by April 2019. World Class failed to pay its loan that year.​
​
June 2021 — Karlin Real Estate took over the property through foreclosure. Karlin planned life-science labs and separately proposed apartments.​
​
March 20, 2026 — Karlin sold the property to SE Cosmos (SB Energy).

6. WHAT THE CITY AND STATE ARE DOING
August 3, 2026 — Gov. Abbott ordered a statewide review of data centers asking to connect to the Texas power grid.​
​
August 25, 2026 — Austin Planning, Austin Energy, and Austin Water briefed City Council on data centers.​
​
August 27, 2026 — Council unanimously voted (Item 61) to start writing data center rules. Council is scheduled to see the proposed rules on November 20 and vote on December 3, 2026. These new rules are not expected to apply to Cosmos, because it was already approved and under construction.​
​
December 9, 2026 — A City Council committee will discuss new rules for very large water users. The public can attend or watch on ATXN.
Power and water levels that trigger extra oversight
LEVEL
WHAT HAPPENS
More than 85 million gallons of water a year
Austin Water treats the customer as a "large volume" user.
20 megawatts or more
The customer must sign a Facilities Extension Agreement with Austin Energy and pay the full cost of new equipment before work begins. City staff must also report these requests to Council. Cosmos is above this level.
25 to 75 megawatts
The state's grid operator, ERCOT, sent a "community impact" survey to some projects of this size that had not yet turned on. We have not seen public confirmation that Cosmos was included.
75 megawatts or more
The project counts as a "large load" under state law (Senate Bill 6) and must go through a special state review. Austin Energy says Cosmos will not be treated as a large data center.

7. WHAT THE CITY PERMITS SHOW
Since October 2025, the City of Austin has issued about 90 construction permits for 6801 River Place Blvd: building, electrical, mechanical (heating and cooling), and plumbing. We reviewed all of them in the City's public permit records on November 8, 2026. Together they show what is being built inside the existing buildings and outside them.
City permits issued since October 2025
~90
City square feet of interior remodeling permitted so far issued since October 2025
~328,000
square feet of new outdoor equipment yard (about 2.7 acres)
117,450
separate power equipment installations labeled for data halls
23
Inside the Building
The campus buildings are divided into numbered "sectors," each with up to four floors. These are the main remodel permits. Most also have their own electrical, mechanical, and plumbing permits.
AREA BEING REMODELED
SIZE
ISSUED
PERMIT
Level 1 of Sectors 3, 6, and 7, and Level 2 of Sectors 3 and 6
96,600 sq ft
Apr 2026
2026-025330 BP
Sector 3, Level 1 (shipping), and Sector 7, Floors 2 to 4
65,700 sq ft
Apr 2026
2026-025331 BP
Sector 3, Floors 3 and 4
38,300 sq ft
May 2026
2026-057402 BP
Sector 6, Floors 3 and 4
37,300 sq ft
May 2026
2026-057401 BP
Sector 2, Floors 3 and 4
37,200 sq ft
May 2026
2026-057403 BP
Sector 2, Levels 1 and 2, and Sector 1, Level 1
32,740 sq ft
Aug 2026
2026-102111 BP
Existing office and lab, Sector 7, Level 2
18,251 sq ft
Jul 2026
2026-077348 BP
Sector 144: wiring, ductwork, plumbing, and a replaced raised floor
1,820 sq ft
Aug 2026
2026-102125 BP
Stronger Floors for Heavy Equipment
Two structural permits from October 2025 reinforce the floor framing "for new loading conditions" in Sectors 142, 143, 146, and 147 on Floors 2 and 3. Inside walls in those same sectors were torn out on Floors 2, 3, and 4 in January 2026. Floors are usually strengthened when much heavier equipment is moving in, such as computer racks and large batteries. The Sector 144 permit also replaces a "raised access floor," the kind of raised floor that hides cables and cooling under computer rooms.
Power Equipment for Data Halls
Twenty-three pairs of building and electrical permits, filed in February 2026 and issued in May and June 2026, each cover a 500 or 335 square foot "New Installation of Tracking Equipment and Inspection." The City's description does not say what the equipment is. The permit labels give more detail:
​
-
UPS-MV-DH1 (2 permits), UPS-MV-DH2 (8 permits), and UPS-MV-DH3 (8 permits)
-
UPS-MV-RL (2 permits)
-
UPS-LV-DH and UPS-LC-DH (3 permits, 335 square feet each)
​
In data center construction, "UPS" usually means an uninterruptible power supply, which is a large battery system that keeps computers running if power drops. "MV" and "LV" usually mean medium and low voltage, and "DH" usually means data hall. Read that way, the permits point to backup power for at least three data halls (DH1, DH2, and DH3). We will ask SB Energy to confirm what this equipment is and where it sits.
Outside the Buildings
-
Parking garage torn down. A parking garage of about 92,430 square feet, built around 1998, was demolished under a permit issued April 6, 2026 (2026-040264 BP). The permit refers to the approved site plan SP-2021-0456C.
-
New exterior equipment yard. A 117,450 square foot "Exterior Equipment Yard" is being built under permits issued in May 2026 (2026-057404 BP, EP, and PP), with its own electrical and plumbing work.
​​
From what we can see, it looks like the servers will be inside the existing office buildings, and the cooling towers and other equipment will be placed in the new equipment yard, where the old parking garage was demolished. Outdoor equipment like this is the most likely source of noise at the property line, which is why the 1984 noise and vibration limits matter so much.
Other Work
-
Bigger freight elevator doors. The freight elevator doors in Sector 3 are being widened from 8 to 10 feet on all four floors (permit 2026-115847 BP, September 2026). That makes room to move very large equipment in and out.
-
New fire line. A fire line (a dedicated water line for fire sprinklers) was permitted in June 2026 (2026-075328 PP).
-
Office circuits. New lighting and power circuits were added to existing office space in Sector 110 in January 2026.
Who is Doing the Work
COMPANY
ROLE ON THE PERMITS
Turner Construction
General contractor on nearly every building permit
Alterman, Inc.
Electrical contractor, including all 23 data hall power permits
The Porter Company
Plumbing and ductworth
Batchelor & Kimball, Inc.
Mechanical contractor (heating and cooling piping)
Big State Electrical
Electrical work on one early office permit
Worker Protections
​Many of these permits went through the City's faster "Expedited Review." Large commercial projects that use it may have to join the Better Builder Program, which sets safety, training, and wage standards for construction workers and uses an independent monitor. A City note on one plumbing permit (2026-025331 PP), dated March 27, 2026, says SE Cosmos "has not met" its Better Builder agreement. Permits issued in August 2026 are labeled "Better Builder," which suggests the agreement was later put in place.
A Note on Dollar Amounts
The construction values on the City permits cannot be relied on. Some permits list $1 for each trade. Others list $305 million for each trade, for a total of $1.5 billion on a single 37,000 square foot remodel. The state filing below ($610 million) and SB Energy's own figure (about $1 billion) are better guides.
Other Filings
-
State filing (TDLR project TABS2026007469): filed December 8, 2025 by the prior owner, Karlin. It covers 234,000 square feet of interior work, including structure, walls, heating and cooling, electrical, plumbing, and computer systems. Work was listed to start March 15, 2026 and finish April 15, 2027, at an estimated cost of $610 million.
-
City Commercial Plan Review 2026-009760 PR: the drawings are not available to the public online.
-
Site plan revision SP-2021-0456C(R2): an update to the approved site plan, still pending with the City.
-
Plan review 2026-014961 PR is labeled "Change of Use to Data Center." City Development Services has said the label is a mistake and is being fixed.
-
SB Energy's SEC filing (Form S-1, filed August 31, 2026, and later updated) has the most detailed public information about the project. We have not seen the S-2 report.